Acme Solar Holdings, through its wholly owned subsidiary Acme Surya Power Private Limited, has successfully commissioned the second phase of its Battery Energy Storage System (BESS) project in Rajasthan. The newly commissioned phase adds 35.714 MW / 160.48 MWh to the project’s capacity.
The BESS project, located in the village of Jaimalsar, Bikaner district, is part of a larger initiative with a total planned capacity of 250 MW / 1103.392 MWh. With the completion of this second phase, Acme Surya Power has now achieved a commissioned capacity of 95.714 MW / 430.086 MWh.
The commercial operation date for this newly commissioned phase is set for 26 March 2026, marking a significant milestone in the project’s timeline.
Disclaimer: This article is based on a regulatory filing submitted to the National Stock Exchange of India (NSE).