KP Energy Limited has successfully commissioned the 6.3MW (Phase-XI) ISTS-connected Wind Power Project at the Sidhpur site in Devbhoomi Dwarka, Gujarat. This phase includes three Wind Turbine Generators (WTGs) of 2.1MW each and forms part of the 250.8MW capacity awarded to Apraava Energy Private Limited by the Solar Energy Corporation of India Limited (SECI) under Tranche-VIII bidding.

Key Highlights:

  1. Phase-XI Commissioning Details:
    • Capacity: 6.3MW, consisting of three WTGs of 2.1MW each.
    • Location: Sidhpur site, Devbhoomi Dwarka, Gujarat.
  2. Project Overview:
    • Total awarded capacity: 250.8MW.
    • Client: Apraava Energy Private Limited.
    • KP Energy’s role: Development under the Land and Balance of Plant Contract.
  3. Cumulative Commissioned Capacity:
    • With this commissioning, the net cumulative capacity at the Sidhpur site now stands at 252MW, surpassing the awarded capacity of 250.8MW. The commissioned phases include:
      • 52.5MW + 29.4MW + 25.2MW + 21MW + 10.5MW + 25.2MW + 29.4MW + 16.8MW + 12.6MW + 23.1MW + 6.3MW.

Strategic Impact:

This achievement underlines KP Energy’s commitment to driving renewable energy projects in India and its collaboration with SECI. By consistently meeting and exceeding project milestones, KP Energy continues to strengthen its presence in the wind energy sector, supporting India’s renewable energy goals.