Acme Solar Holdings has announced the commissioning of the third phase of its Battery Energy Storage System (BESS) project in . The newly operational phase adds 11.429 MW / 51.354 MWh to the project, which is located in Jaimalsar, Bikaner.

The third phase is part of a larger project with a total capacity of 250 MW / 1103.392 MWh. With this latest addition, Private Limited, a wholly owned subsidiary of , has now achieved a commissioned capacity of 107.143 MW / 481.440 MWh.

The commercial operation date for this phase is set for 31 March 2026, marking another milestone in the development of renewable energy infrastructure in the region.