Aditya Ultra Steel Limited (AUSL) has announced two key decisions from its board meeting held on March 31, 2025:

  1. Revised timeline for 5000 KWP Solar Captive Power Plant

  2. Termination of MoU with Maheshwar Ispat Pvt. Ltd.

Solar Plant Timeline Revised

The company has updated the tentative timeline for its 5000 KWP solar captive power plant due to changes in regulatory policies that delayed connectivity. The revised schedule is:

  • CEIG approval: by end of May 2025

  • Installation & commissioning: by end of July 2025

  • Post-commissioning approvals (GEDA, UGVCL, CEIG): by end of September 2025

Any material development on the plant’s operations or financial impact will be disclosed in due course.

MoU with Maheshwar Ispat Terminated

AUSL also announced the termination of its Memorandum of Understanding (MoU) with Maheshwar Ispat Pvt. Ltd., which was related to the manufacturing of TMT bars.

Reason for termination:

The company stated it has now achieved full utilization of its TMT bar production capacity, eliminating the need for the collaboration.

These disclosures were made in compliance with Regulation 30 of SEBI (LODR) Regulations, 2015.