PNC Infratech Limited has successfully completed the Improvement and Upgradation of NH-731 (Pkg-III) in Uttar Pradesh, executed by its subsidiary Hardoi Highways Private Limited under the Hybrid Annuity Model (HAM) worth Rs 864 crore. The project, spanning from Km 175.080 to Km 229.070, was provisionally completed on January 18, 2025, an impressive 168 days ahead of schedule.

The National Highways Authority of India (NHAI) awarded this contract under NH(O) to enhance road infrastructure, ensuring safer and smoother travel. The Provisional Completion Certificate (PCOD) was issued on February 26, 2025, enabling the project’s commercial operations.

Key Project Details:

  • Contract Type: Hybrid Annuity Model (HAM)
  • Project Cost: ₹864 Crore (plus price index adjustments)
  • Scheduled Completion: July 5, 2025
  • Actual Completion: January 18, 2025
  • Early Completion Bonus: ₹14.18 Crore from NHAI

This remarkable achievement underscores PNC Infratech’s efficiency in infrastructure development, delivering projects ahead of time while maintaining top-quality standards.