NTPC Limited has announced the successful trial operation of Unit-3 (660 MW) of the North Karanpura Super Thermal Power Project (3×660 MW). With the achievement of approved norms and due approvals, the unit is now officially included in NTPC’s installed capacity.

Following this addition, NTPC’s total installed capacity has risen to 60,266 MW on a standalone basis and 81,368 MW on a group basis. This marks another milestone in NTPC’s continued expansion of power generation capacity across India.

In the exchange filing, the company shared, “We wish to inform that based on achievement of approved norms and due approvals, Unit-3 of 660 MW capacity of North Karanpura Super Thermal Power Project, (3 x 660 MW) has successfully completed trial operation and consequently included in the installed capacity of NTPC Limited. With this, the total installed capacity of NTPC on standalone and group basis has become 60266 MW and 81368 MW respectively.”

TOPICS: NTPC